As of 9/9/2022, after some significant breakthroughs during the night’s work, the contractors and PGE were able to verify to their (and PSU’s) satisfaction that the new electrical control system is working as designed.

Nightly power down testing is over. Unless some unforeseen problems crop up, we should be done with powerdown testing until our next (one night) annual test somewhere in the future.

We’ll be powering up department office printers, primary department office desktops, major computer labs, and select systems that people requested. Let us know if there are specific systems that you would like powered up for you.

Thanks to everyone for your patience.